Actions from previous PMF: |
E-mail web location of CMS VME documentation to Paul Dauncey, RH, 19-12-2003, SQ to check with Paul, done
Provide support & consultancy for testing as required IC/SAB Ongoing
Investigate & provide support for power sequencing issues, JS, 19-12-2003, ongoing, will follow up when the firmware is in place and the board is drawing full operating current
Provide consultancy for BE/VME FPGA, ST/EF, Ongoing
Make sure Route Cards & Problem Reports up to date, SAB, 19-12-2003, ongoing
Update Project Spec and sign off, RH/PD, 15-12-2003, SQ to check with Paul
Test NIM to LVDS module, SAB, 30-11-2004, will be done if required for testing |
Actions for this PMF: |
|