PMF Number: | 29 |
Project Manager: | Rob Halsall / Steve Quinton |
Date of PMF: | 5 Mar 2004 |
Date Submitted: | 5 Mar 2004 |
News and Comment: | The last phone meeting was held on 3/3/04. The next will be at 1.00 pm
on 11/03/04. Progress has been made with the firmware and testing is now underway using the VFE card. Once this is completed the plan is to move the test setup to Imperial. There is a circuit fault on one set of front end channels, Adam will investigate when the board is available. |
Actions from previous PMF: | Provide support & consultancy for testing as required IC/SAB
Ongoing Investigate & provide support for power sequencing issues, JS, 19-12-2003, ongoing, will follow up when the firmware is in place and the board is drawing full operating current Provide consultancy for BE/VME FPGA, ST/EF, Ongoing Make sure Route Cards & Problem Reports up to date, SAB, 19-12-2003, ongoing Update Project Spec and sign off, RH/PD, 15-12-2003, SQ to check with Paul Test NIM to LVDS module, SAB, 30-11-2004, will be done if required for testing |
Actions for this PMF: | Provide support & consultancy for testing as required IC/SAB
Ongoing Investigate & provide support for power sequencing issues, JS, 19-12-2003, ongoing - some progress with this but further work required Provide consultancy for BE/VME FPGA, ST/EF, Ongoing Make sure Route Cards & Problem Reports up to date, SAB, 19-12-2003, ongoing Update Project Spec and sign off, RH/PD, 15-12-2003, SQ and PD need to meet Test NIM to LVDS module, SAB, 30-11-2004, will be done if required for testing |
Milestone | Milestones from Project Management Plan | Date due in PMP | Status |
---|---|---|---|
1 | Prototype Design Complete | 31 May 2003 | Completed on 4 Aug 2003 |
2 | Prototype Fabrication Complete | 30 Jun 2003 | Completed on 27 Nov 2003 |
3 | Prototype Testing Complete | 30 Nov 2003 | Predicted on 31 Mar 2004 |
4 | Design iteration complete | 28 Feb 2004 | Predicted on 29 Apr 2004 |
5 | Production board fabrication complete | 31 Mar 2004 | Predicted on 31 May 2004 |
6 | Production Board Testing complete | 31 May 2004 | Predicted on 30 Jul 2004 |
Staff Booking Data for this Financial Year (when this PMF was
created)
(units are in percentage of staff-month, i.e. 100 = 1
staff-month. Staff Booking predictions are shown in blue.)
Person | Cost Code | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Jan | Feb | Mar | Total (SM) |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Rob Halsall | FD31720 | 10 | 10 | 10 | 0 | 0 | 0 | 10 | 25 | 25 | 25 | 10 | 10 | 1.35 |
Adam Baird | FD31720 | 70 | 60 | 60 | 60 | 60 | 60 | 80 | 50 | 50 | 25 | 25 | 25 | 6.25 |
Edward Freeman | FD31720 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 25 | 25 | 25 | 25 | 25 | 1.25 |
Totals | 0.8 | 0.7 | 0.7 | 0.6 | 0.6 | 0.6 | 0.9 | 1 | 1 | 0.75 | 0.6 | 0.6 | 8.85 SM (0.74 SY) |
Is the Project proceeding on Schedule? y
Is the Project proceeding on
Budget? y
Comments and Corrective Actions: