PMF Number: | 30 |
Project Manager: | Rob Halsall / Steve Quinton |
Date of PMF: | 19 Mar 2004 |
Date Submitted: | 19 Mar 2004 |
News and Comment: | The last phone meeting was held on 18/3/04 The prototype board has been successfully tested with the VFE card and the test setup, with board 002, has been moved to IC. Firmware development continues at IC with Adam et al providing support as required. Prototype 001 remains at RAL. There is an intermittent fault on this board which Adam is investigating and work continues on the power sequencing. Testing in Paris could begin in early April. Successful completion of the Paris tests is milestone 3. A rapid decision will then be required on the need to revise the design for production (leading to milestone 4). |
Actions from previous PMF: | Provide support & consultancy for testing as required IC/SAB
Ongoing Investigate & provide support for power sequencing issues, JS, 19-12-2003, ongoing - some progress with this but further work required Provide consultancy for BE/VME FPGA, ST/EF, Ongoing Make sure Route Cards & Problem Reports up to date, SAB, 19-12-2003, ongoing Update Project Spec and sign off, RH/PD, 15-12-2003, SQ and PD need to meet Test NIM to LVDS module, SAB, 30-11-2004, will be done if required for testing |
Actions for this PMF: | Provide support & consultancy for testing as required IC/SAB
Ongoing Investigate & provide support for power sequencing issues, JS, 19-12-2003, ongoing - some progress with this but further work required Provide consultancy for BE/VME FPGA, ST/EF, Ongoing Make sure Route Cards & Problem Reports up to date, SAB, 19-12-2003, ongoing Update Project Spec and sign off, RH/PD, 15-12-2003, SQ and PD need to meet Test NIM to LVDS module - done |
Milestone | Milestones from Project Management Plan | Date due in PMP | Status |
---|---|---|---|
1 | Prototype Design Complete | 31 May 2003 | Completed on 4 Aug 2003 |
2 | Prototype Fabrication Complete | 30 Jun 2003 | Completed on 27 Nov 2003 |
3 | Prototype Testing Complete | 30 Nov 2003 | Predicted on 31 Mar 2004 |
4 | Design iteration complete | 28 Feb 2004 | Predicted on 29 Apr 2004 |
5 | Production board fabrication complete | 31 Mar 2004 | Predicted on 31 May 2004 |
6 | Production Board Testing complete | 31 May 2004 | Predicted on 30 Jul 2004 |
Staff Booking Data for this Financial Year (when this PMF was
created)
(units are in percentage of staff-month, i.e. 100 = 1
staff-month. Staff Booking predictions are shown in blue.)
Person | Cost Code | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Jan | Feb | Mar | Total (SM) |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Rob Halsall | FD31720 | 10 | 10 | 10 | 0 | 0 | 0 | 10 | 25 | 25 | 25 | 10 | 10 | 1.35 |
Adam Baird | FD31720 | 70 | 60 | 60 | 60 | 60 | 60 | 80 | 50 | 50 | 25 | 25 | 25 | 6.25 |
Edward Freeman | FD31720 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 25 | 25 | 25 | 25 | 25 | 1.25 |
Totals | 0.8 | 0.7 | 0.7 | 0.6 | 0.6 | 0.6 | 0.9 | 1 | 1 | 0.75 | 0.6 | 0.6 | 8.85 SM (0.74 SY) |
Is the Project proceeding on Schedule? y
Is the Project proceeding on
Budget? y
Comments and Corrective Actions: