PMF Number: | 32 |
Project Manager: | Rob Halsall |
Date of PMF: | 2 Apr 2004 |
Date Submitted: | 2 Apr 2004 |
News and Comment: | Paul Dauncey has collected 001 from RAL
Adam is not likely to be available to travel over to Paris The milestones will be reviewed when the Paris tests are complete |
Actions from previous PMF: | Provide support & consultancy for testing as required IC/SAB Ongoing
Investigate & provide support for power sequencing issues, JS, 19-12-2003, ongoing - minor changes in timing required to reduce current spikes Provide consultancy for BE/VME FPGA, ST/EF, done Make sure Route Cards & Problem Reports up to date, SAB,done, all PRs completed Update Project Spec and sign off, RH/PD, 15-12-2003, SQ and PD need to meet |
Actions for this PMF: | Provide support & consultancy for testing as required IC/SAB Ongoing
Investigate & provide support for power sequencing issues, JS, 19-12-2003, ongoing - minor changes in timing required to reduce current spikes Update Project Spec and sign off, RH/PD, 15-12-2003, RH and PD need to meet |
Milestone | Milestones from Project Management Plan | Date due in PMP | Status |
---|---|---|---|
1 | Prototype Design Complete | 31 May 2003 | Completed on 4 Aug 2003 |
2 | Prototype Fabrication Complete | 30 Jun 2003 | Completed on 27 Nov 2003 |
3 | Prototype Testing Complete | 30 Nov 2003 | Predicted on 31 Mar 2004 |
4 | Design iteration complete | 28 Feb 2004 | Predicted on 29 Apr 2004 |
5 | Production board fabrication complete | 31 Mar 2004 | Predicted on 31 May 2004 |
6 | Production Board Testing complete | 31 May 2004 | Predicted on 30 Jul 2004 |
Staff Booking Data for this Financial Year (when this PMF was created)
(units are in percentage of staff-month, i.e. 100 = 1 staff-month.
Staff Booking predictions are shown in blue.)
Person | Cost Code | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Jan | Feb | Mar | Total (SM) |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Totals | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 SM (0.00 SY) |
Is the Project proceeding on Schedule? y
Is the Project proceeding on Budget? y
Comments and Corrective Actions: