PMF Number: | 36 |
Project Manager: | Rob Halsall |
Date of PMF: | 29 Apr 2004 |
Date Submitted: | 29 Apr 2004 |
News and Comment: | Phone Meeting has been held - 29-04-2004 at 3pm - the minutes will be at the following link;
http://www.hep.ph.ic.ac.uk/calice/elecMeetings/040429phone/minutes.txt All equipment is at Paris except CERC S/N-01 which has bee returned due to problems. CERC-01 was put straight onto JTAG on receipt at RAL and has passed the JTAG tests. Further testing will be carried out to attempt to replicate the problems seen at Paris. The tests have gone well but there are some unresolved intermittent noise issues which are currently not understood but are most likely a system grounding or shielding problem. The VFE V3 is not available yet, expected 24 May, so tests will have to be repeated around this time. |
Actions from previous PMF: | Provide support & consultancy for testing as required IC/SAB Ongoing
Investigate & provide support for power sequencing issues, JS, 19-12-2003, ongoing - minor changes in timing required to reduce current spikes Update Project Spec and sign off, RH/PD, 15-12-2003, RH and PD need to meet |
Actions for this PMF: | SAB to investigate noise problems in Paris, SAB, End May
Provide support & consultancy for testing as required IC/SAB Ongoing Investigate & provide support for power sequencing issues, JS, 19-12-2003, ongoing - minor changes in timing required to reduce current spikes Update Project Spec and sign off, RH/PD, 15-12-2003, RH and PD need to meet |
Milestone | Milestones from Project Management Plan | Date due in PMP | Status |
---|---|---|---|
1 | Prototype Design Complete | 31 May 2003 | Completed on 4 Aug 2003 |
2 | Prototype Fabrication Complete | 30 Jun 2003 | Completed on 27 Nov 2003 |
3 | Prototype Testing Complete | 30 Nov 2003 | Predicted on 31 Mar 2004 |
4 | Design iteration complete | 28 Feb 2004 | Predicted on 29 Apr 2004 |
5 | Production board fabrication complete | 31 Mar 2004 | Predicted on 31 May 2004 |
6 | Production Board Testing complete | 31 May 2004 | Predicted on 30 Jul 2004 |
Staff Booking Data for this Financial Year (when this PMF was created)
(units are in percentage of staff-month, i.e. 100 = 1 staff-month.
Staff Booking predictions are shown in blue.)
Person | Cost Code | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Jan | Feb | Mar | Total (SM) |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Totals | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 SM (0.00 SY) |
Is the Project proceeding on Schedule? y
Is the Project proceeding on Budget? y
Comments and Corrective Actions: