PMF Number: | 39 |
Project Manager: | Rob Halsall |
Date of PMF: | 21 May 2004 |
Date Submitted: | 21 May 2004 |
News and Comment: | Rob Halsall met with Paul Dauncey on 18-05-2004 to discuss Spec & plans for 2004-2005.
Paul Dauncey took CERC-001 and associated equipment on 18-05-2004 for tests in Paris Next Meeting is a phone meeting via Rob Halsall's Office on 26-05-2004 |
Actions from previous PMF: | Make correct version of schemtaics & layout available, SAB, 21-05-2004
Get problem reports ready for review, SAB, 28-05-2004 Investigate ADC & DAC ranges, SAB, 28-05-2004 Investigate Power sequencing & configuration problems, SAB, 28-05-2004 Investigate reducing the NIM2LVDS module latency, SAB, 28-05-2004 Write User Guide for CERC in word/pdf format, SAB, 28-05-2004 Order new USB2 Compact Flash programmer on Calice budget, SAB, 21-05-2004 Borrow 3 or 4 SCSI cables for Paris Tests, SAB, 21-05-2004 SAB to investigate noise problems in Paris, SAB, End May Update Project Specs & Plans for 2004/5 and sign off, RH/PD, 26-05-2003 |
Actions for this PMF: | Make correct version of schemtaics & layout available, SAB, 21-05-2004
Get problem reports ready for review, SAB, 28-05-2004 Investigate ADC & DAC ranges, SAB, 28-05-2004 Investigate Power sequencing & configuration problems, SAB, 28-05-2004 Investigate reducing the NIM2LVDS module latency, SAB, 28-05-2004 Write User Guide for CERC in word/pdf format, SAB, 28-05-2004 Order new USB2 Compact Flash programmer on Calice budget, SAB, 21-05-2004 Borrow 3 or 4 SCSI cables for Paris Tests, SAB, 21-05-2004 SAB to investigate noise problems in Paris, SAB, End May Update Project Specs & Plans for 2004/5 and sign off, RH/PD, 26-05-2003 |
Milestone | Milestones from Project Management Plan | Date due in PMP | Status |
---|---|---|---|
1 | Prototype Design Complete | 31 May 2003 | Completed on 4 Aug 2003 |
2 | Prototype Fabrication Complete | 30 Jun 2003 | Completed on 27 Nov 2003 |
3 | Prototype Testing Complete | 30 Nov 2003 | Predicted on 31 May 2004 |
4 | Design iteration complete | 28 Feb 2004 | Predicted on 29 Jun 2004 |
5 | Production board fabrication complete | 31 Mar 2004 | Predicted on 31 Aug 2004 |
6 | Production Board Testing complete | 31 May 2004 | Predicted on 30 Sep 2004 |
Staff Booking Data for this Financial Year (when this PMF was created)
(units are in percentage of staff-month, i.e. 100 = 1 staff-month.
Staff Booking predictions are shown in blue.)
Person | Cost Code | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Jan | Feb | Mar | Total (SM) |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Totals | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 SM (0.00 SY) |
Is the Project proceeding on Schedule? n
Is the Project proceeding on Budget? n
Comments and Corrective Actions:
Project Spec will be updated shortly to reflect new schedule & budget for 2004-2005